[PWA 2010] How to avoid user fill timesheet for old projects?

Discussion in 'SharePoint Blogs' started by /u/legendgodgod, Mar 30, 2017.

Thread Status:
Not open for further replies.
  1. /u/legendgodgod

    /u/legendgodgod Guest

    Blog Posts:
    0
    Our company fiscal year start at 1st April and end at 31 March. We have setup 2 project: Project FY2016 & Project FY2017. In FY2016 project all tasks end at 31 March. All tasks in FY2017 start at 1st April.

    When user open the timesheet this week (our timesheet start from Monday and end at Sunday), they can see both FY2016 and 2017's tasks. They can fill in hours for both project's tasks on all 7 days. Hence user may fill in wrong projects (e.g. fill in the Monday hours in FY2017 tasks)

    Can it be avoided by configure PWA?

    submitted by /u/legendgodgod